WorldLink
TU Logo
Detailed Cost Estimate & Design Dossier
District Rate F.Y. 2082/083  |  Long wall / short wall takeoff

Bhadaure Toilet Models

Five Sanitation Designs — Drawings, Quantities & Costs

Bhadaure Eco-Sanitation Team · IOE Pulchowk

The Sanitation Challenge

Bhadaure is a sloped, water-scarce Dalit settlement on expansive red-clay soil. Standard pour-flush + soak-pit toilets are often unfeasible here. These five models give a graded menu — from a cheap waterless unit to a full piped-water toilet — each fully costed at district rates.

37.5% Sanitation Deficit

Many households share toilets or practise open defecation.

Impermeable Clay

Soak-pits fail in the expansive red clay across sloped terrain.

Water Scarcity

Long water-fetch times limit water-reliant pour-flush systems.

Community Equity

Households ready to contribute labour & local materials.

The Five Toilet Models at a Glance
Option 1
Brick · CGI · SATO
Option 2
Ferro-cement · Steel pan
Option 3
Brick · RCC · Tank + Basin
Option 4
Stone · Slate
Option 5
UDDT (waterless)
Each model is detailed next — drawings, quantities and full specifications.
All Five Working Drawings
Opt 1
Opt 1
Brick · CGI · SATO
Opt 2
Opt 2
Ferro-cement · Steel pan
Opt 3
Opt 3
Brick · RCC · Tank + Basin
Opt 4
Opt 4
Stone · Slate
Opt 5
Opt 5
UDDT (waterless)

Each design is dimensioned with a plan and a section (millimetres). Detailed drawings follow per option.

3D Walkthrough — Toilet Model
Shared Construction System

All five models share the same foundation and floor build-up; they differ in their walls, roof and sanitation fixture.

Floor build-up (top → down)
12 mm non-slip stone flooringwet-area safe finish
50 mm cement punningsmooth screed
100 mm PCC 1:3:6sub-base concrete
Brick soling (1 flat layer)load distribution
Sand filling, compactedlevelling layer
Rammed earthcompacted subgrade
Foundation

350 mm stone footing + M20 RC plinth / sill / lintel bands; trench 0.45 m × 0.40 m.

RC bands

Plinth + sill + lintel bands in M20 (1:1.5:3), 100 mm deep, tie the walls together — important on Bhadaure’s sloping, expansive-clay ground.

Option 1 — Brick · CGI · SATO
Option 1 drawing
Option 1

Brick · CGI · SATO

Low-cost brick toilet with corrugated-sheet roof and a water-saving SATO pour-flush pan.

Pour-flush · minimal water
Estimated cost / unit
Rs 135,434
Option 1 — Design Concept
Pour-flush · minimal water

A simple brick room over a SATO pour-flush pan. Its self-sealing trap opens only when flushed — blocking odour and flies while using barely a litre of water, ideal for water-scarce Bhadaure. Waste is led to an offset pit/tank.

Among the lowest-cost options — simple brick box

SATO self-sealing pan needs very little water (good for water-scarce Bhadaure)

Familiar brick masonry — local masons can build it

Light CGI roof — easy to carry and fix

Option 1 — Floor Plan
Option 1 plan
Footprint1.46 m × 1.66 m
Internal clear1.00 m × 1.20 m
Walls230 mm brick masonry
Plan dimensions (mm)

600, 520, 400, 300 (×4) mm

Option 1 — Cross-Section
Option 1 section
Overall height2.40 m
Roof30 mm CGI corrugated sheet
Plinth≈ 450 mm above GL
Section dimensions (mm)

2400 (wall ht), 1975 (door), 450 (plinth), 300, 150 mm

Option 1 — Sanitation System & Fixtures
SATO pour-flush pan

Self-sealing trap; ~1 L per flush

Timber door

0.75 × 1.95 m leaf

Ventilator

0.45 × 0.45 m, cross-airflow

Option 1 — Construction Build-up
Roof (top → down)
30 mm CGI corrugated sheetmono-pitch, sheds rain
50 × 75 mm timber battenssupport framing
Walls
230 mm brick masonry (1:4)+ 12 mm cement plaster
Floor build-up
12 mm non-slip stone flooringwet-area safe finish
50 mm cement punningsmooth screed
100 mm PCC 1:3:6sub-base concrete
Brick soling (1 flat layer)load distribution
Sand filling, compactedlevelling layer
Rammed earthcompacted subgrade
Foundation

350 mm stone footing + M20 RC plinth / sill / lintel bands; trench 0.45 m × 0.40 m.

Option 1 — Materials & Specifications
External footprint1.46 m × 1.66 m
Internal clear1.00 m × 1.20 m
Walls230 mm brick masonry (1:4)
Overall height2.40 m
Roof30 mm CGI corrugated sheet on 50×75 timber battens
Substructure350 mm stone footing + RC plinth/sill/lintel bands
Sanitary fixtureSATO pour-flush pan + P/S trap
Door / window0.75 × 1.95 m / 0.45 × 0.45 m
Option 1 — Bill of Quantities

Quantities by long wall / short wall · District Rate F.Y. 2082/083.

#Item of WorkUnitQtyRateAmount (Rs)
1Earthwork in excavation (ordinary soil)m^31.044554579
2Stone masonry (II class) 1:6 c/s — substructurem^30.3046,2201,894
3RC beam & sill bands, M20 1:1.5:3, 100 mmm^30.24513,2373,239
4Compacted earth fillm^30.240857206
5Sand fillm^30.1202,742329
6Brick soling, 1 flat layerm^21.2008581,029
7PCC 1:3:6, 100 mm thickm^30.12011,1991,344
850 mm cement-sand screed / punning floorm^21.2008341,001
912 mm non-slippery stone (slate) flooringm^21.2001,7372,085
101st class brickwork in 1:4 c/s mortar — wallsm^32.30913,67531,573
1112 mm cement plaster 1:4m^222.20649210,927
12Woodwork for frames (Sal) — door & windowm^30.051221,28111,197
13Woodwork for shutters (panelled)m^21.3579,32612,655
14Roof timber — rafters 75x50 + battens 50x25m^30.063141,1018,889
15CGI sheet roofing, 0.5 mm incl. fixingm^22.7871,1083,089
16Reinforcement, TMT bars (cut/bend/fix)kg28.8201363,928
17Steps — mass concrete M20m^30.42512,8285,456
18SATO pan setset1.0003,3773,377
Option 1 — Cost Summary
Works Sub-total (A)Rs 102,796
Add: Contingencies (4% of A)Rs 4,112
Add: Carriage by tractor (5.8 km off-road + 1.1 km paved)Rs 12,945
Add: VAT (13%)Rs 15,581
FINAL AMOUNT (per unit)Rs 135,434
Carriage
Rs 12,945
Labour (in works)
Rs 22,084
Option 1 — Strengths & Best Fit

Among the lowest-cost options — simple brick box

SATO self-sealing pan needs very little water (good for water-scarce Bhadaure)

Familiar brick masonry — local masons can build it

Light CGI roof — easy to carry and fix

Best fit

Households wanting an affordable, durable masonry toilet where a small amount of water is available for the SATO pan.

Final cost per unit
Rs 135,434
Option 2 — Ferro-cement · Steel pan
Option 2 drawing
Option 2

Ferro-cement · Steel pan

Lightweight, fast-to-build ferro-cement shell — the cheapest of the five models.

Ferro-cement shell · dry squat
Estimated cost / unit
Rs 66,863
Option 2 — 3D Visualisation
Option 2 3D view
Option 2 3D view
Option 2 — Design Concept
Ferro-cement shell · dry squat

A thin ferro-cement shell (steel wire-mesh plastered with 1:3 cement mortar) forms the walls and roof in one light, monolithic piece — fast and cheap. A stainless-steel squat pan serves the user; no RC bands are required.

Lightest structure — least material to carry to site

Fast to cast; thin wire-mesh + mortar shell

Cheapest model overall

Steel pan is robust and reusable

Option 2 — Floor Plan
Option 2 plan
Footprint1.12 m × 1.32 m
Internal clear1.02 m × 1.22 m
Walls~40–50 mm ferro-cement shell
Plan dimensions (mm)

1120, 600, 520, 500, 400 (×2), 300 (×4), 230 mm

Option 2 — Cross-Section
Option 2 section
Overall height2.40 → 2.625 m (mono-pitch)
RoofFerro-cement / light CGI sheet
Plinth≈ 450 mm above GL
Section dimensions (mm)

2625 / 2400 (mono-pitch), 450 (plinth), 150 mm

Option 2 — Sanitation System & Fixtures
Steel squat pan

Durable stainless pan + trap

Ferro-cement shell

~40–50 mm walls & roof

Door & vent

Light openings

Option 2 — Construction Build-up
Roof (top → down)
10 mm corrugated / ferro rooflight mono-pitch
Ferro-cement shellwire-mesh + 1:3 mortar
Walls
~40–50 mm ferro-cement shell (wire-mesh + 1:3 mortar)monolithic shell
Floor build-up
12 mm non-slip stone flooringwet-area safe finish
50 mm cement punningsmooth screed
100 mm PCC 1:3:6sub-base concrete
Brick soling (1 flat layer)load distribution
Sand filling, compactedlevelling layer
Rammed earthcompacted subgrade
Foundation

350 mm stone footing + M20 RC plinth / sill / lintel bands; trench 0.45 m × 0.40 m.

Option 2 — Materials & Specifications
External footprint1.12 m × 1.32 m
Internal clear1.02 m × 1.22 m
Walls~40–50 mm ferro-cement shell (wire-mesh + 1:3 mortar)
Overall height2.40 → 2.625 m (mono-pitch)
RoofFerro-cement / light CGI sheet
Substructure350 mm stone footing (no RC bands — monolithic shell)
Sanitary fixtureStainless-steel squat pan + trap
Door / window0.75 × 1.95 m / 0.45 × 0.45 m
Option 2 — Bill of Quantities

Quantities by long wall / short wall · District Rate F.Y. 2082/083.

#Item of WorkUnitQtyRateAmount (Rs)
1Earthwork in excavation (ordinary soil)m^31.058554587
2Stone masonry (II class) 1:6 c/s — substructurem^30.3096,2201,920
3Compacted earth fillm^30.249857213
4Sand fillm^30.1242,742341
5Brick soling, 1 flat layerm^21.2448581,068
6PCC 1:3:6, 100 mm thickm^30.12411,1991,393
750 mm cement-sand screed / punning floorm^21.2448341,038
812 mm non-slippery stone (slate) flooringm^21.2441,7372,162
9Ferro-cement shell ~40 mm (wall & roof)m^211.6462,32627,083
10Woodwork for shutters (panelled)m^21.0009,3269,326
11Reinforcement, TMT bars (cut/bend/fix)kg5.510136751
12Steps — mass concrete M20m^30.20012,8282,566
13Steel pan setset1.0004,1824,182
Option 2 — Cost Summary
Works Sub-total (A)Rs 52,629
Add: Contingencies (4% of A)Rs 2,105
Add: Carriage by tractor (5.8 km off-road + 1.1 km paved)Rs 4,436
Add: VAT (13%)Rs 7,692
FINAL AMOUNT (per unit)Rs 66,863
Carriage
Rs 4,436
Labour (in works)
Rs 17,997
Option 2 — Strengths & Best Fit

Lightest structure — least material to carry to site

Fast to cast; thin wire-mesh + mortar shell

Cheapest model overall

Steel pan is robust and reusable

Best fit

The most budget-constrained households, or where rapid, lightweight construction is the priority.

Final cost per unit
Rs 66,863
Option 3 — Brick · RCC · Tank + Basin
Option 3 drawing
Option 3

Brick · RCC · Tank + Basin

Full-service brick toilet with a flat RCC roof, roof-top water tank and a hand-wash basin.

Piped water · pan + wash basin
Estimated cost / unit
Rs 156,933
Option 3 — 3D Visualisation (Exterior)
Overtank toilet 3D exterior
front view
aerial view
Option 3 — 3D Visualisation (Interior & System)
interior squat pan and basin
Inside: Orissa pan, tiled dado, grilled window & external wash basin
full sanitation system
System: roof tank + vent pipe feeding the pan & basin, with twin septic chambers
Option 3 — Design Concept
Piped water · pan + wash basin

The full-service model: a brick room with a flat RCC roof that carries a 500 L tank. Gravity-fed water supplies the pan and a wash-hand basin, giving a complete, modern wash facility wherever a water source exists.

Piped water from a 500 L roof-top tank — supports flushing & hand-washing

Includes a complete wash-basin point (basin + pedestal + CP tap)

Durable flat RCC roof — long service life

Highest service level of the five

Option 3 — Floor Plan
Option 3 plan
Footprint1.66 m × 1.46 m
Internal clear1.20 m × 1.00 m
Walls230 mm brick masonry
Plan dimensions (mm)

3010, 1660, 1460, 1200, 1000, 750 (×2), 480, 300 (×2), 230 (×2) mm

Option 3 — Cross-Section
Option 3 section
Overall height2.40 m
Roof100 mm RCC slab
Plinth≈ 450 mm above GL
Section dimensions (mm)

2400 (wall ht), 1975 (door), 450 (plinth), 300, 150, 125 (×2) mm

Option 3 — Sanitation System & Fixtures
Orissa pan + P/S trap

Pour-flush WC

500 L overhead tank

Gravity-fed supply

Wash basin + CP tap

Hand-washing point

Door & glazed window

Lit, ventilated

Option 3 — Construction Build-up
Roof (top → down)
100 mm RCC slab (M20)flat structural roof
500 L PVC tankroof-top, gravity feed
Walls
230 mm brick masonry (1:4)+ 12 mm cement plaster
Floor build-up
12 mm non-slip stone flooringwet-area safe finish
50 mm cement punningsmooth screed
100 mm PCC 1:3:6sub-base concrete
Brick soling (1 flat layer)load distribution
Sand filling, compactedlevelling layer
Rammed earthcompacted subgrade
Foundation

350 mm stone footing + M20 RC plinth / sill / lintel bands; trench 0.45 m × 0.40 m.

Option 3 — Materials & Specifications
External footprint1.66 m × 1.46 m
Internal clear1.20 m × 1.00 m
Walls230 mm brick masonry (1:4)
Overall height2.40 m
Roof100 mm RCC slab (M20) — flat roof carrying the tank
Substructure350 mm stone footing + RC bands
Sanitary fixtureOrissa pan + 500 L overhead PVC tank + wash basin (CP tap)
Door / window0.75 × 1.95 m / 0.45 × 0.45 m
Option 3 — Bill of Quantities

Quantities by long wall / short wall · District Rate F.Y. 2082/083.

#Item of WorkUnitQtyRateAmount (Rs)
1Earthwork in excavation (ordinary soil)m^31.044554579
2Stone masonry (II class) 1:6 c/s — substructurem^30.3046,2201,894
3RC beam & sill bands, M20 1:1.5:3, 100 mmm^30.24513,2373,239
4Compacted earth fillm^30.240857206
5Sand fillm^30.1202,742329
6Brick soling, 1 flat layerm^21.2008581,029
7PCC 1:3:6, 100 mm thickm^30.12011,1991,344
850 mm cement-sand screed / punning floorm^21.2008341,001
912 mm non-slippery stone (slate) flooringm^21.2001,7372,085
101st class brickwork in 1:4 c/s mortar — wallsm^32.30913,67531,573
1112 mm cement plaster 1:4m^222.20649210,927
12Woodwork for frames (Sal) — door & windowm^30.051221,28111,197
13Woodwork for shutters (panelled)m^21.3579,32612,655
14RCC slab roof, M20 1:1.5:3 (excl. steel/formwork)m^30.24214,5373,524
15Formwork / shuttering for slabm^22.4241,0602,568
16Reinforcement, TMT bars (cut/bend/fix)kg57.3601367,818
17Steps — mass concrete M20m^30.42512,8285,456
18Sanitary — Orissa pan set (pan+trap+conn.)set1.0005,8785,878
19Overhead PVC water tank 500 L (set)set1.0009,0789,078
20Wash basin set (basin+pedestal+trap+CP tap+connection)set1.0008,0058,005
Option 3 — Cost Summary
Works Sub-total (A)Rs 120,384
Add: Contingencies (4% of A)Rs 4,815
Add: Carriage by tractor (5.8 km off-road + 1.1 km paved)Rs 13,679
Add: VAT (13%)Rs 18,054
FINAL AMOUNT (per unit)Rs 156,933
Carriage
Rs 13,679
Labour (in works)
Rs 25,612
Option 3 — Strengths & Best Fit

Piped water from a 500 L roof-top tank — supports flushing & hand-washing

Includes a complete wash-basin point (basin + pedestal + CP tap)

Durable flat RCC roof — long service life

Highest service level of the five

Best fit

Sites with a reliable water source — gives the most complete, modern wash facility.

Final cost per unit
Rs 156,933
Option 4 — Stone · Slate
Option 4 drawing
Option 4

Stone · Slate

Traditional load-bearing stone masonry with a local slate roof.

Stone masonry · slate roof
Estimated cost / unit
Rs 149,752
Option 4 — 3D Visualisation
Option 4 3D view
Option 4 3D view
Option 4 3D view
Option 4 — Design Concept
Stone masonry · slate roof

A traditional load-bearing stone toilet with a local slate roof — durable and in keeping with the village vernacular. A pour-flush Orissa pan is used. The heavy 350 mm walls give long life but high carriage unless stone is local.

Uses local stone & slate — fits the vernacular

Very durable, heavy load-bearing walls

Natural materials, low embodied cement

Heaviest — highest carriage if stone is not sourced locally

Option 4 — Floor Plan
Option 4 plan
Footprint1.90 m × 1.70 m
Internal clear1.20 m × 1.00 m
Walls350 mm stone masonry
Plan dimensions (mm)

1900, 1700 (×2), 1200, 1000, 750 (×2), 600, 350, 300 (×2) mm

Option 4 — Cross-Section
Option 4 section
Overall height2.10 → 2.315 m (mono-pitch)
RoofLocal slate tiles
Plinth≈ 450 mm above GL
Section dimensions (mm)

2315 / 2100 (mono-pitch), 1050, 600, 450 (plinth), 320, 190, 175, 150 mm

Option 4 — Sanitation System & Fixtures
Orissa pan + P/S trap

Pour-flush WC

Stone masonry walls

350 mm load-bearing

Slate roof

Natural, durable tiles

Option 4 — Construction Build-up
Roof (top → down)
75 mm (3") slate tileslocal flag-stone
100 × 75 mm battenstile support
75 mm (3") raftersroof framing
Walls
350 mm stone masonry (1:4)+ 12 mm cement plaster
Floor build-up
12 mm non-slip stone flooringwet-area safe finish
50 mm cement punningsmooth screed
100 mm PCC 1:3:6sub-base concrete
Brick soling (1 flat layer)load distribution
Sand filling, compactedlevelling layer
Rammed earthcompacted subgrade
Foundation

350 mm stone footing + M20 RC plinth / sill / lintel bands; trench 0.45 m × 0.40 m.

Option 4 — Materials & Specifications
External footprint1.90 m × 1.70 m
Internal clear1.20 m × 1.00 m
Walls350 mm stone masonry (1:4)
Overall height2.10 → 2.315 m (mono-pitch)
RoofLocal slate tiles on timber rafters/battens
Substructure350 mm stone footing + RC bands
Sanitary fixtureOrissa pan + P/S trap
Door / window0.75 × 1.95 m / 0.45 × 0.45 m
Option 4 — Bill of Quantities

Quantities by long wall / short wall · District Rate F.Y. 2082/083.

#Item of WorkUnitQtyRateAmount (Rs)
1Earthwork in excavation (ordinary soil)m^31.044554579
2Stone masonry (II class) 1:6 c/s — substructurem^30.3046,2201,894
3RC beam & sill bands, M20 1:1.5:3, 100 mmm^30.40613,2375,374
4Compacted earth fillm^30.240857206
5Sand fillm^30.1202,742329
6Brick soling, 1 flat layerm^21.2008581,029
7PCC 1:3:6, 100 mm thickm^30.12011,1991,344
850 mm cement-sand screed / punning floorm^21.2008341,001
912 mm non-slippery stone (slate) flooringm^21.2001,7372,085
10Stone masonry (I class) 1:4 c/s — wallsm^33.4917,25925,344
11Woodwork for frames (Sal) — door & windowm^30.051221,28111,197
12Woodwork for shutters (panelled)m^21.3579,32612,655
13Roof timber — rafters 75x50 + battens 50x25m^30.084141,10111,796
14Slate roofing on battensm^26.4772,04013,211
15Reinforcement, TMT bars (cut/bend/fix)kg47.8101366,516
16Steps — mass concrete M20m^30.42512,8285,456
17Sanitary — Orissa pan set (pan+trap+conn.)set1.0005,8785,878
Option 4 — Cost Summary
Works Sub-total (A)Rs 105,893
Add: Contingencies (4% of A)Rs 4,236
Add: Carriage by tractor (5.8 km off-road + 1.1 km paved)Rs 22,395
Add: VAT (13%)Rs 17,228
FINAL AMOUNT (per unit)Rs 149,752
Carriage
Rs 22,395
Labour (in works)
Rs 23,009
Option 4 — Strengths & Best Fit

Uses local stone & slate — fits the vernacular

Very durable, heavy load-bearing walls

Natural materials, low embodied cement

Heaviest — highest carriage if stone is not sourced locally

Best fit

Where stone & slate are available near the site — durable and traditional, but watch the carriage cost.

Final cost per unit
Rs 149,752
Option 5 — UDDT (waterless)
Option 5 drawing
Option 5

UDDT (waterless)

Urine-diverting dry toilet — waterless, raised on a twin collection vault. The eco-sanitation answer for Bhadaure.

Waterless · twin-vault · eco-san
Estimated cost / unit
Rs 146,217
Option 5 — 3D Visualisation
Option 5 3D view
Option 5 3D view
Option 5 3D view
Option 5 — Design Concept
Waterless · twin-vault · eco-san

A waterless urine-diverting dry toilet (UDDT). The special pan separates urine (drained at the front) from faeces (dropped into one of two sealed vaults). A full vault rests and composts while the second is used — yielding safe soil conditioner. No water, no soak-pit: the strongest fit for Bhadaure’s clay soil.

Completely WATERLESS — ideal where water is scarce

Urine diversion + twin vaults = safe reuse / composting

No soak-pit needed — suits the impermeable red-clay soil

True eco-sanitation; nutrients returned to farmland

Option 5 — Floor Plan
Option 5 plan
Footprint1.66 m × 1.46 m
Internal clear1.20 m × 1.00 m
Walls230 mm brick masonry
Plan dimensions (mm)

3010, 1660, 1460, 1200, 1000, 750 (×2), 480, 300 (×2), 230 mm

Option 5 — Cross-Section
Option 5 section
Overall height2.30 m
RoofMetal roofing sheet
Plinth≈ 450 mm above GL
Section dimensions (mm)

2300, 1050, 1000 (×2), 600, 500, 200, 150 (×3), 100 mm

Option 5 — Sanitation System & Fixtures
UD diverting pan

Urine front, faeces rear

Vent pipe

Dries vault, controls odour

Twin collection vaults

Alternating fill / compost

Access steps

Raised floor ~1.0 m

Option 5 — Construction Build-up
Roof (top → down)
25 mm metal roofing sheetmono-pitch
100 × 75 mm battenssheet support
75 mm (3") raftersframing
Walls
230 mm brick masonry (1:4)+ 12 mm cement plaster
Floor build-up
12 mm non-slip stone flooringwet-area safe finish
50 mm cement punningsmooth screed
100 mm PCC 1:3:6sub-base concrete
Brick soling (1 flat layer)load distribution
Sand filling, compactedlevelling layer
Rammed earthcompacted subgrade
Foundation

350 mm stone footing + M20 RC plinth / sill / lintel bands; trench 0.45 m × 0.40 m.

Option 5 — Materials & Specifications
External footprint1.66 m × 1.46 m
Internal clear1.20 m × 1.00 m
Walls230 mm brick masonry (1:4), raised ~1.0 m on a twin vault
Overall height2.30 m
RoofMetal roofing sheet on timber rafters/battens
SubstructureRaised twin vault + RCC cover slab + steps
Sanitary fixtureUDDT urine-diverting pan + vent pipe + twin masonry vaults
Door / window0.75 × 1.95 m / 0.45 × 0.45 m
Option 5 — Bill of Quantities

Quantities by long wall / short wall · District Rate F.Y. 2082/083.

#Item of WorkUnitQtyRateAmount (Rs)
1Earthwork in excavation (ordinary soil)m^31.044554579
2Stone masonry (II class) 1:6 c/s — substructurem^30.3046,2201,894
3RC beam & sill bands, M20 1:1.5:3, 100 mmm^30.24513,2373,239
4Compacted earth fillm^30.240857206
5Sand fillm^30.1202,742329
6Brick soling, 1 flat layerm^21.2008581,029
7PCC 1:3:6, 100 mm thickm^30.12011,1991,344
850 mm cement-sand screed / punning floorm^21.2008341,001
912 mm non-slippery stone (slate) flooringm^21.2001,7372,085
101st class brickwork in 1:4 c/s mortar — wallsm^32.41713,67533,046
1112 mm cement plaster 1:4m^221.14249210,404
12Woodwork for frames (Sal) — door & windowm^30.051221,28111,197
13Woodwork for shutters (panelled)m^21.3579,32612,655
14Roof timber — rafters 75x50 + battens 50x25m^30.063141,1018,889
15CGI sheet roofing, 0.5 mm incl. fixingm^22.7871,1083,089
16Reinforcement, TMT bars (cut/bend/fix)kg42.9501365,854
17Steps — mass concrete M20m^30.42512,8285,456
18RCC slab roof, M20 1:1.5:3 (excl. steel/formwork)m^30.12014,5371,744
19Formwork / shuttering for slabm^21.2001,0601,272
20UDDT urine-diverting pan setset1.0006,0226,022
Option 5 — Cost Summary
Works Sub-total (A)Rs 111,332
Add: Contingencies (4% of A)Rs 4,453
Add: Carriage by tractor (5.8 km off-road + 1.1 km paved)Rs 13,610
Add: VAT (13%)Rs 16,821
FINAL AMOUNT (per unit)Rs 146,217
Carriage
Rs 13,610
Labour (in works)
Rs 23,546
Option 5 — Strengths & Best Fit

Completely WATERLESS — ideal where water is scarce

Urine diversion + twin vaults = safe reuse / composting

No soak-pit needed — suits the impermeable red-clay soil

True eco-sanitation; nutrients returned to farmland

Best fit

Bhadaure’s flagship eco-san solution — works with no water and on expansive clay where soak-pits fail.

Final cost per unit
Rs 146,217
How the Estimates Are Built

Every item uses a District Rate Analysis (DRA) to the F.Y. 2082/083 rate book.

A

Material cost (cement, brick, stone, sand, steel…)

B

Labour (skilled + unskilled days × wage)

C

Tools & plant = 3% of labour

D

Overhead & profit = 15%

Analysed rate $= (A + B + C)\times 1.15$   →   then per item: Quantity × Rate
Quantities are taken off by the long wall / short wall method, verified against the option drawings.
Carriage — by Tractor (District Rate)

Materials travel from the vendor to the site by tractor: 5.8 km on a rough tractor-only road + 1.1 km on pitched (paved) road.

Tractor-only road · 5.8 km

District Rate 2082/083 — Rs 14.00 / quintal·km (ट्र्याक्टर मात्र चल्ने सडक).

Paved road · 1.1 km

District Rate — Rs 3.45 / quintal·km (पक्की सडक).

Load + unload

Handling charge — Rs 0.55/kg (easy) or Rs 1.15/kg (fragile).

Carriage $=$ Weight (quintal) $\times$ Lead (km) $\times$ Rate $+$ load/unload
Because a tractor can reach the site, carriage is ~75–80% lower than the earlier mule assumption; local sourcing of sand/stone trims it further.
Cost Comparison — All Five Models
ModelWorksLabour*CarriageVAT 13%FINAL (Rs)
Opt 1 · Brick · CGI · SATO102,79622,08412,94515,581135,434
Opt 2 · Ferro-cement · Steel pan52,62917,9974,4367,69266,863
Opt 3 · Brick · RCC · Tank + Basin120,38425,61213,67918,054156,933
Opt 4 · Stone · Slate105,89323,00922,39517,228149,752
Opt 5 · UDDT (waterless)111,33223,54613,61016,821146,217

*Labour is already included inside the works figure (shown for information, not added again). Each rate also loads 3% tools + 15% overhead & profit.

Per-Unit Final Cost

Option 2 (ferro-cement) is cheapest; Option 3 (flush · tank · wash basin) is dearest — driven by its richer works content. With tractor carriage, transport is no longer the main cost driver.

What Drives Each Cost

Stacked build-up: works + 4% contingency + carriage + 13% VAT.

Carriage by Model

By tractor (District Rate 2082/083) carriage is far below mule haulage. Heavy stone (Opt 4) and brick (Opt 1, 3, 5) still carry the most weight; load/unload is a fixed handling charge.

Labour Content by Model

Direct wages embedded in the works rates — skilled @ Rs 1,150/day, unskilled @ Rs 585/day.

Service Level vs. Affordability
OptionWater needDurabilityCost (Rs)
Opt 1 · Brick · CGI · SATOLowHigh135,434
Opt 2 · Ferro-cement · Steel panLowMedium66,863
Opt 3 · Brick · RCC · Tank + BasinHighHigh156,933
Opt 4 · Stone · SlateLowVery high149,752
Opt 5 · UDDT (waterless)NoneHigh146,217
Best value for Bhadaure: Option 5 (UDDT) for waterless eco-san, or Option 2 for the tightest budget.
The Leach Pit & Interconnection

Each toilet discharges to a leach pit. A complete disposal system = one pit type (dry or wet) + one interconnection. Quantities are sized for 5 users; rates include tractor carriage (Rs 139.99/quintal), 4% contingency and 13% VAT.

Dry leach pit

Single pit, honeycomb-brick lining + RCC cover slab. Suits low-water toilets (SATO / squat / pour-flush).

WorksRs 12,310
Final · incl. carriage+VATRs 16,696

Wet twin-circular pit

Twin pits, deeper, with extra honeycomb lining. Essential for the flush toilet (Option 3) and its higher water load.

WorksRs 16,795
Final · incl. carriage+VATRs 22,664

Interconnection · Alt 1

75 mm pipes + bifurcation chamber — the lower-cost connection.

FinalRs 4,106

Interconnection · Alt 2

Covered brick drains — slightly higher cost, no pipework.

FinalRs 5,445
Complete Pit Systems (5 users)
System · pit + interconnectionFinal (Rs)
Dry pit + Alt 1 · piped + chamber  lowest29,641
Dry pit + Alt 2 · covered drain32,581
Wet twin pit + Alt 1 · piped + chamber38,134
Wet twin pit + Alt 2 · covered drain41,075
A complete system = one pit type (dry OR wet) + one interconnection (Alt 1 OR Alt 2).
Materials take-off · all four components
Cement4.09 bag
Sand0.58 m³
Aggregate0.18 m³
Brick cl.75785 nos
TMT steel14.75 kg
75 mm pipe3 m
Skilled4.82 days
Unskilled11.78 days
Grand Total — Toilet + Leach-Pit System
OptionToilet only+ Dry·Alt 1+ Dry·Alt 2+ Wet·Alt 1+ Wet·Alt 2
Opt 1 · Brick · CGI · SATO135,434156,236157,575162,205163,544
Opt 2 · Ferro-cement · Steel pan66,86387,66589,00493,63394,973
Opt 3 · Brick · RCC · Tank + Basin156,933183,703185,043
Opt 4 · Stone · Slate149,752170,554171,893176,523177,862
Opt 5 · UDDT (waterless)146,217167,019168,358172,987174,327
Option 3 (flush + tank) uses the wet twin pit only — dry-pit cells show “—”.
Option 5 (UDDT) is waterless — its twin vaults are the disposal, so a leach pit is optional (greywater only).
Grand total = per-unit toilet cost + chosen complete pit system · all figures Rs, incl. carriage + 13% VAT.
Which Model, Which Context?
Opt 1
Brick · CGI · SATO
Households wanting an affordable, durable masonry toilet where a small amount of water is available for the SATO pan.
Rs 135,434
Opt 2
Ferro-cement · Steel pan
The most budget-constrained households, or where rapid, lightweight construction is the priority.
Rs 66,863
Opt 3
Brick · RCC · Tank + Basin
Sites with a reliable water source — gives the most complete, modern wash facility.
Rs 156,933
Opt 4
Stone · Slate
Where stone & slate are available near the site — durable and traditional, but watch the carriage cost.
Rs 149,752
Opt 5
UDDT (waterless)
Bhadaure’s flagship eco-san solution — works with no water and on expansive clay where soak-pits fail.
Rs 146,217
Cost vs. Context for Bhadaure

No water? → UDDT

Option 5 is waterless and needs no soak-pit — the strongest fit for Bhadaure’s clay soil and water scarcity.

Tight budget? → Ferro-cement

Option 2 is the cheapest at Rs 66,863, light to carry, quick to build.

Water available? → Brick + RCC

Option 3 gives piped water, a wash basin and a durable roof for full service.

Simple & affordable → Brick + CGI

Option 1 is a familiar, low-cost masonry toilet with a water-saving SATO pan.

Local stone? → Stone + slate

Option 4 is durable and traditional; with tractor access its carriage is modest — cheaper still if stone & slate are sourced locally.

Carriage now modest

With tractor access at District Rate, carriage is only ~10–20% of works — no longer the main driver. Local sand/stone trims it further.

Key Takeaways

The UDDT (Option 5, Rs 146,217) is the best technical fit for Bhadaure — waterless and soak-pit-free.

Option 2 (ferro-cement, Rs 66,863) is the lowest-cost; Option 3 (flush · tank · basin, Rs 156,933) is the highest, due to its richer works content.

Carriage is by tractor at District Rate 2082/083 (5.8 km tractor-only road + 1.1 km paved + load/unload) — far below mule haulage; local sourcing trims it further.

All quantities use the long wall / short wall method at District Rate 2082/083, verified against the option drawings.

Scope, Assumptions & Caveats

Included

Civil works, sanitary fixtures, roof, steps, labour, tools, 15% OH&P, 4% contingency, carriage and 13% VAT.

Excluded

Land, water-source development, approach works, electrical, and any site-specific foundation upgrades.

Assumptions

Internal clear 1.2×1.0 m; brick 230 mm, stone 350 mm, ferro ~50 mm; mono-pitch roofs use average eave height.

To confirm

Pitched-road vehicle rate (assumed Rs 8/q·km), fixture market prices, and whether stone/sand are locally available.

Implementation Roadmap
1
Community choice

Present these five costed options; let households pick by water access, budget and soil.

2
Confirm rates

Lock fixture prices and the pitched-road vehicle rate; check local stone/sand sourcing.

3
Detailed design

Finalise foundations & vault details for the chosen model on each plot.

4
Mobilise

Procure materials, arrange carriage, schedule masons with community labour.

5
Build & monitor

Construct, inspect against the QCS, and document for the next phase.

Community Contribution Lowers Cost

The estimates price all labour at district wage rates. Bhadaure’s households are ready to contribute “sweat equity” — which directly reduces the cash cost.

Unskilled labour

Households can do excavation, carriage assistance, and helper work — a large share of the unskilled days.

Local materials

Stone, sand and aggregate gathered locally cut both material and carriage costs sharply.

Cash saving

Every unskilled day contributed saves ~Rs 585; local sourcing can save tens of thousands on carriage.

The figures shown are the full cost; community contribution makes the real cash outlay lower.

Thank You

Five fully-costed sanitation designs for the Bhadaure settlement — ready for community selection and tendering.

Bhadaure Eco-Sanitation Team · IOE Pulchowk Campus · District Rate F.Y. 2082/083